All contractors performing PLA - Covered Work need to request a pre-job conference by doing the following:
- All pre-job conference meeting requests must be received seven (7) days before the desired date.
- To request a meeting, the General Contractor must:
- Turn in a completed pre-job conference form (no additions will be accepted)
- Turn in a signed Letter of Assent (LOA)
- Turn in a completed Local Worker Hiring Plan
- Please Note: Each contractor (all tiers) must have a representative present to assign work. General Contractors are not able to announce/assign work on behalf of another contractor (all tiers).
- PLA Letter of Assent (2021) - projects with a bid advertisement date or request for proposal advertisement date on or after January 1, 2021
- PLA Letter of Assent (1999 - 2020) - active projects or projects bid/advertised prior to December 31, 2020
- PLA Craft Employee Request Form (2021) - dated 09/03/20
- PLA Craft Employee Request Form (1999 - 2020) - dated 10/01/16